Q8 Engine Replacement (TN612)

Preparations

Read the instructions carefully before starting, and leave yourself time to perform the work.

You will need to have the following tools to hand:

  • Flat screwdriver
  • Replacement MOD-Q8-ENG.

Ensure you have taken appropriate anti-static precautions

Avoid working in areas with synthetic floor coverings or carpet, especially polypropylene material, as opposed to natural materials such as solid wood or wool. Ideally work at a proper workbench with ESD safe features, such as a metal frame. Before work, try to discharge yourself into a mains earth fitment, water pipe etc.

This is important as parts of the equipment are static sensitive and even if any damage is not immediately obvious, so called “latent damage” can occur, where a device may be partially degraded yet continue to perform its intended function. However, the operating life of the device may be reduced dramatically, leading to premature failure.

If you are unsure about any part of the procedure, seek advice before proceeding.

 

 


 

Before you start, shut down the console, switch it off, and remove the power leads.

Engine Replacement Procedure

Remove the Old Engine

Remove the 4 x Thumbscrews on the engine.

Remove the ribbon cable and connectors paying attention to the connector locks under the connectors.

Q8 engine connections from factory.jpg

 

Fitting the new Engine

Place the new engine in the engine slot and re-connect the cables.

Switch the console on.

‘Hardware change detected’ dialog box will appear.

2.jpg

Click on Unlock and run Setup.

Allow the console to Restart.

Quantum Setup Utility will open. Click Setup. Configuring devices appears on the screen.

3.jpg

 

Once done, Setup successful message will be displayed.

4.jpg

 

Next follow the on-screen prompt as highlighted.

Click exit.

Go to Quantum Home>Advanced settings> Configure All. This will configure the left, centre and right screens in the appropriate position and Orientation confirmed by the screen highlighted in blue in the respective screens.

5.jpg

 

Configuration Successful message will be displayed.

6.jpg

Next calibrate touchscreens.

Warning- Screen will be very bright for the next few steps.

Follow the on-screen instructions to tap the screen with a finger. Press Enter.

7.jpg

 

Follow the same procedure for the next two screens.

Once all the screens are done, Calibration Successful message will be displayed.

8.jpg

 

Click Yes on the Configuration successful to lock and Restart.

The console will restart and boot into the Quantum Application software.

Repeat this procedure with the second Engine if necessary, as prompted by the Hardware change detection utility.

 

 